CBS completed a comprehensive façade-remediation programme at Apollo Apartments, an existing block of 55 homes in central Bristol. The works included replacement of insulated render, non-compliant fire stopping, metal cladding and associated flashings across the building’s external envelope. while the building remained occupied.
Apollo Apartments
Project Overview
Unite Facades Ltd appointed CBS to address fire-safety deficiencies within the external envelope of Apollo Apartments.
The occupied development contains 55 apartments at Baldwin Street in central Bristol. CBS’s scope included the full removal and reinstallation of the insulated-render façade, replacement of non-compliant fire stopping, and removal and renewal of metal cladding and flashings.
The £900,000 programme was delivered over 28 weeks and completed in October 2023.
The project required the façade components to be treated as an integrated system, with the performance of the completed envelope dependent on careful coordination between insulation, render, fire stopping, cladding, openings and perimeter details.
The building remained occupied throughout the works. Resident liaison was led by Unite Facades Ltd, allowing CBS to focus on the planned remediation sequence and specialist installation activities.
Challenge / Requirements
The works needed to address identified fire-safety deficiencies while managing a substantial removal and reinstatement programme across an existing residential building.
Access and logistics were constrained by the central Bristol location and the need to work around residents, neighbours and public areas.
The façade incorporated several interdependent systems. Insulated render, fire stopping, metal cladding and flashings needed to be removed and replaced in the correct sequence, with interfaces inspected before new construction concealed them.
Weather protection and resident communication were also important throughout the 28-week programme.
Solution / Approach
CBS established a phased programme of façade removal and reinstatement to maintain control of safety, weather exposure and quality.
Existing insulated render and cladding were removed systematically, allowing concealed substrates and fire-stopping arrangements to be reviewed.
Non-compliant fire stopping was replaced before the approved insulation, render, metal cladding and flashings were installed. Interfaces around openings, changes in material and floor zones were checked before completed areas were closed.
The site team coordinated access, scaffolding, deliveries, waste removal and temporary protection around the occupied development. Working areas were kept controlled and organised to reduce the impact of the works on residents and surrounding properties.
Inspections and photographic quality records were completed throughout the process. This provided evidence of concealed fire-safety measures and helped maintain consistency across the different elevations.
Regular liaison with Unite Facades Ltd supported timely decisions and alignment between site findings, design information and the programme.
The replacement façade incorporated Wetherby systems, installed in coordination with the approved fire-stopping and associated cladding interfaces.
Results / Outcome
The works were completed on programme in October 2023, providing Apollo Apartments with a renewed external envelope incorporating Wetherby systems, compliant fire stopping, metal cladding and flashings.
The building remained occupied throughout, with resident liaison managed by Unite Facades Ltd. The project addressed the identified façade deficiencies while retaining the functionality of the 55-home development.
Successful delivery supported an ongoing relationship with Unite Facades Ltd, with CBS subsequently working with the client on several further schemes.
Maintaining programme certainty within the occupied city-centre development also provided a strong reference point for later façade-remediation commissions delivered with the same client.