CBS completed a ten-week summer refresh programme at New Bridewell Street in central Bristol. The £300,000 internal fit-out package included drylining, carpentry and decoration, delivered within a defined seasonal programme for Watkin Jones PLC. ahead of the student intake.

Business CBS Fire & Fit Out
Client Watkin Jones PLC
Location New Bridewell, Nelson Street, Bristol, BS1 2BA
Scope Internal fit-out
Value £300,000
Duration Duration 10 weeks
Completion September 2025

Project Overview

Watkin Jones PLC appointed CBS to undertake internal fit-out works at New Bridewell Street in Bristol.

The project was delivered as a summer refresh programme, with a scope covering internal drylining, carpentry and decoration.

CBS coordinated the trade packages across the agreed work areas and managed the sequence from initial preparation through to completed finishes.

The £300,000 programme was completed over ten weeks in September 2025.

The location and seasonal delivery period required structured planning of labour, materials, access and inspections so that works could be completed before the building returned to its normal operating cycle.

The student-accommodation refresh covered 27 rooms and included strip-out, internal patching and repairs, new flooring, decorations and final completion works.

Challenge / Requirements

The project needed to be delivered within a fixed ten-week summer window.

Drylining, carpentry and decoration had to progress in a clear sequence, with each package dependent on completed and inspected preceding work.

Work within the central Bristol location also required careful management of deliveries, storage and waste movements.

The principal requirement was to complete the refresh efficiently without compromising workmanship, allowing sufficient time for snagging, rectification and final handover before the building returned to full use.

The accommodation comprised 27 rooms, so consistency across repetitive work areas and close control of final finishes were important to the quality of handover.

Solution / Approach

CBS developed a room-by-room or area-by-area sequence for the drylining, carpentry and decorating packages.

Existing areas were reviewed before work began so that required repairs, new construction and retained elements could be identified.

Drylining works were completed first, including the necessary framing, boardwork and preparation for finishing. Carpentry was coordinated around door openings, trims, fittings and other detailed elements.

Decoration followed once the substrates and completed construction had been inspected and accepted.

Labour and materials were planned against the ten-week programme, with regular progress reviews used to identify constraints or areas requiring additional resource.

The site team coordinated deliveries and waste removal around the city-centre setting and maintained communication with Watkin Jones PLC throughout the works.

Inspection and snagging were incorporated into the programme rather than left until the final days, supporting a more controlled handover.

The room-based sequence also gave the site team a clear basis for monitoring completion, closing snags promptly and releasing finished areas without delaying the remaining programme.

Results / Outcome

CBS completed the £300,000 refresh programme on time in September 2025, allowing all 27 student rooms to be handed back before the September intake.

The strip-out, repairs, flooring, decorations and finishing works were delivered without variations, providing a controlled outcome within the fixed ten-week summer window.

This was CBS’s first project with Watkin Jones PLC. Successful delivery helped establish the relationship and led to a significantly larger collaboration at Grosvenor House in Bath.

The absence of variations also reflects the value of defining the scope clearly and maintaining a consistent approach across every room.